Project Summary
- BASD Signed MoU with the national bank of Kuwait “NBK” to support the Rural Communities. The first phase of the project in Egypt was in Minya governorate on 2020 to build 60 household biogas units.
- The second phase of the project in Gao Gharb village, Temaa city in Sohag governorate on 2021. the Project will start on June 2021 and planned to finish on June 2022. BASD supervises designing, building, Installing, Installation testing, and maintenance of units.
- we suppose that Temaa will has the greatest number of Households Biogas units installed in Sohag Governorate with 67% of total installed units in Sohag Governorate.
BASD supposed to train 6 of recent graduate’s engineers, and 6 of masons on the mechanism of units building and installation.
Throughout the project BASD look forward to establish new 3 startups company to join the market:
Project data
Client: National Bank of Kuwait-Egypt
Doner: National Bank of Kuwait-Egypt
Location: Sohag Governorate
project Duration: June 2021- June 2022
Type of feedstock: cattle manure
Capacity of feedstock: 1,642,500 kg/y
Capacity of production: 67,890 m³/y
Project Budget: 1,500,000 EGP
Related Projects
Installation of 50 household biogas units in Gharbia governorate:
Project studyEYE project Egypt Youth Employment is one of ILO project that intended create job opportunities in the promotion of decent employment in the rural economy in Egypt. EYE in collaboration with BASD plan to install 50 Household Biogas Units with 3 cubic...
Installation of 21 Household Biogas units in Luxor governorates
Project studyBASD partnering with Small Grants Program “SGP” on 2020 to install 21 household biogas units with 3 cubic meters capacity in Luxor governorate. the Project will start on November 2021 and planned to finish on July2022. BASD supervises...
Installation of 60 household biogas units in Minya
Project studySmall Grants Program “SGP” in collaboration with BASD has funded Al shorouk Association on 2020 to install 60 household biogas units with 3 cubic meters capacity in Minya governorate. the Project will start on November 2021 and planned to finish on...